How WaterPave permeable concrete is installed

WaterPave is a patented, single-pour permeable concrete, placed by trained installers on a free-draining sub-base. Here’s each load spec, how a project runs from first call to final inspection, and the numbers behind it.

RMRyan McGovernLead chemist & formulator, Infinity Effects26 Nov 2026 · 5 min read
WaterPave · Permeable

Concrete that lets the rain through: how it’s installed.

WaterPave is a patented, single-pour permeable concrete. Its admixtures lock the stone together, and every build-up is matched to the loads it carries and how fast the ground drains. Here’s how a WaterPave project runs, from first call to final inspection.

  • 30,000+ mm/hinfiltration rate, tested to ASTM C1701
  • 21–32 MPatypical compressive strength
  • 20%connected voids
  • 50+ yearsstructural design life
WaterPave and Infinity Effects crew on site in Australia
WaterPave Australia · On site in AustraliaSee the job →
The build-ups

Four specs, matched to the load.

Pick what the surface has to carry. Typical depths from WaterPave’s specifications; final depths are confirmed for each site.

  1. The finished surface: stone locked together with cement and WaterPave admixtures. Rain passes through its open voids while it carries the load.

    Depth
    100 mm
    Use
    Garden paths, public footpaths and landscaped areas with foot traffic only
  2. At least 35% voids. It supports the slab and holds water while it soaks away.

    Depth
    Confirmed for each site
  3. Water returns to the soil and tops up groundwater. The design is matched to how fast your soil drains.

How a project runs

From first call to final inspection.

WaterPave is placed and finished by trained installers. Here’s each stage of the job.

  1. 1

    Consultation

    Tell us what the project is, where it is and roughly how big. A rough size is fine to start.

    TipPlanning a front garden or a large site? Our site prep guide covers drainage rules and what decides the build-up.

  2. 2

    Site inspection and proposal

    The site is inspected, and you receive a proposal with the build-up for your ground and loads: the depth of the wearing course and the sub-base, matched to how fast your soil drains.

  3. 3

    The sub-base

    A free-draining sub-base of compacted stone screenings, with at least 35% voids, goes down over the natural ground. It supports the slab and holds water while it soaks away.

  4. 4

    The single pour

    WaterPave is a single-pour system. Trained installers place and finish the surface to the depth in your proposal: typically 100 mm for pedestrian areas, 125 mm for driveways, 150 mm for commercial access lanes and car parks, and 300 mm for heavy duty.

    TipChoose from seven standard colours, with custom variations on request.

  5. 5

    Fit-out

    It fits out like any car park. Standard line-marking paint, cat’s-eye reflectors, safety bollards and permanent concrete wheel stops all fix straight onto the surface.

    TipAn approved clear sealer can be applied after installation.

  6. 6

    Completion

    A final inspection, plus guidance on looking after your surface.

    TipOur care guide covers sweeping, keeping the voids clear and cleaning.

WaterPave crew on site beside the concrete truck chute
WaterPave Australia · On site with the mixer · February 2026See the job →
Performance

The numbers behind it.

WaterPave’s published test data. Typical values, given for guidance.

1

Permeable

30,000+ mm/h surface infiltration, tested to ASTM C1701: about 8.3 litres through every square metre, every second.

2

Strong

21–32 MPa typical compressive strength, by mix design.

3

Open

20% voids: a connected network for water and air.

4

Sure-footed

P5 wet rating, pendulum value 88, to AS 4586-2013.

5

Long-lived

50+ years structural design life, from an engineer’s car park review.

6

Load-bearing

Up to 10 t on the standard installation, more on request.

Source: WaterPave Australia technical data sheet TDS001, October 2026. How quickly water leaves the whole build-up depends on the sub-base and the ground beneath. Confirm suitability and design for your project before specifying.

Where it’s used

Real spaces, real impact.

Pick a setting.

Driveways

A clean, modern driveway that drains as it rains, with no puddles at the front door.

Garden paths and patios

Paths and patios that stay usable in wet weather.

Pool surrounds

Splash water drains straight through, and the surface carries a P5 wet slip rating.

FAQ

Questions we get asked

What is WaterPave?

A permeable concrete: a rigid surface with a connected network of open voids, so rain passes through into a free-draining sub-base and on into the ground. Its admixtures lock the stone together, which sets it apart from standard no-fines porous concrete.

How fast does it drain?

Over 30,000 mm an hour at the surface, tested to ASTM C1701. How quickly water leaves the whole build-up depends on the sub-base and the ground beneath.

How thick is it?

Typically 100 mm for pedestrian areas, 125 mm for driveways, 150 mm for commercial access lanes and car parks, and 300 mm for heavy duty. Final depths are confirmed for each site.

What loads can it take?

Up to 10 t on the standard installation, more on request. The heavy-duty spec is designed for heavy rigid vehicles, permeable roads and emergency vehicles.

Is it slippery when wet?

It has a P5 wet rating, with a pendulum value of 88 to AS 4586-2013.

What colours are there?

Seven standard colours, with custom variations on request. Ask for a physical sample before you choose.

Downloads & tools
Having it done?Find an Infinity-trained installer near youFind an installerInstalling it yourself?Learn the system at an Infinity Effects certified schoolSee the training