How to install P.HB Screed over concrete or tiles

P.HB Poly Screed goes straight over prepared concrete or sound tiles at 3 mm. Here’s each build-up, every step from prep to cure, the timings and how much you’ll need.

RMRyan McGovernLead chemist & formulator, Infinity Effects26 Nov 2026 · 8 min read
P.HB Screed · Resin

Over concrete or tiles, one flexible screed.

P.HB Poly Screed is a fast-curing, high-impact polyaspartic hybrid screed that flexes with movement in the floor. Laid at 3 mm over R.S.P Primer and AdhesiMesh Lite, it’s a finished floor on its own, or the base for Spray Granite, Spray Stone or a decorative pour.

  • 3 mmlaid thickness
  • ≈ 3 m²per 15 kg kit
  • 2 h · 20 mingel time, Slow Set · Fast Set
  • 48 h · 6–8 hback in use, Slow Set · Fast Set
The same kitchen floor with the screed going down over the tiles
Fitters’ Showcase · Screed going over the tilesSee the job →
The build-ups

Three build-ups, four layers each.

Concrete, straight over tiles, or as the base for a decorative finish. Tap a layer for the product, coverage and timings.

  1. Spread with a squeegee or rubber grout trowel for continuous, even coverage: no dry patches, pooling, missed edges or excess build-up.

    Coverage
    About 7.5 m² per kg on dense concrete
    Porous
    Medium porosity takes 1.5×, high porosity 2×
  2. Pre-cut to suit the area, laid into the wet primer and pressed flat, with no wrinkles, folds or raised sections. Recommended on concrete to reinforce the screed.

    Rolls
    1 m × 50 m and 1 m × 100 m
    Overlaps
    Allow about 10%
  3. A UV-stable aliphatic polyaspartic hybrid screed, mixed 4:1:1 (screed mix : Part A : Part B), poured onto the reinforced floor and levelled with a flat trowel at 3 mm. It flexes with movement in the floor and reduces the risk of cracking.

    Coverage
    About 3 m² per 15 kg kit at 3 mm
    Gel time
    Slow Set 2 hours · Fast Set 20 minutes
    Colours
    White, POLY colours or any RAL match
  4. A clear water-based sheen coat over the screed, rolled on evenly.

    Coverage
    About 15 m² per kg
Step by step

The install, one step at a time.

These steps follow our P.HB Poly Screed application guide. Set everything up before you mix: with Fast Set, the clock starts fast.

  1. 1

    Check the floor

    It must be sound, dry, stable, clean and free of contamination. Look for laitance, old coatings, oil, grease, adhesive residue, loose concrete, cracks, holes and unsound repairs.

    TipDon’t use the screed to make up for an unstable, contaminated or poorly prepared floor, and never lay it over standing water, condensation or wet cleaning residue.

  2. 2

    Prepare concrete or tiles

    Concrete: grind to CSP 2–3 where practicable, taking extra care at edges, corners, doorways, drains and perimeters, and repair cracks, voids, holes and damaged edges. Tiles: take up loose, broken or cracked tiles, fill the gaps, deep grout joints and holes, degrease and remove all cleaner residue, then sand to take off the gloss and give a key.

    TipOur prep guide has the detail for each floor, including the porosity test.

    • Floor grinder, diamond tooling
    • Edge grinder
    • PolyFuse MAX filler
  3. 3

    Vacuum

    Industrially vacuum the whole area, leaving no loose dust anywhere.

    • Industrial vacuum
  4. 4

    Prime

    Mix R.S.P Primer and spread it with a squeegee or rubber grout trowel for continuous, even coverage, with no dry patches, pooling, missed edges or excess build-up. Porous concrete takes more primer: 1.5× for medium porosity and 2× for high; tiles take 1.5×.

    • Squeegee
    • Rubber grout trowel
  5. 5

    Lay the mesh

    Pre-cut AdhesiMesh Lite to suit the area, avoiding small offcuts. Lay it into the wet primer and press it firmly so it lies flat, with no wrinkles, folds or raised sections. Keep it continuous through doorways, repairs, tile joints, transitions and perimeters, with no loose mesh sticking up.

    TipMesh is required over tiles to bridge the joints, and recommended on concrete.

    • Knife or scissors
    • Measuring tape
  6. 6

    Mix the screed

    Use complete, matched kits and never estimate ratios. Combine Part A and Part B and mix for at least 30 seconds, then add the screed mix gradually while mixing. Keep going for 2–3 minutes until it’s uniform and fully wetted, with no lumps or dry pockets, scraping the sides and base.

    TipDon’t add water, solvent or additives unless we’ve authorised them, and don’t leave mixed material sitting in the bucket.

    • Mixing drill
    • Heavy-duty paddle
    • Clean containers
  7. 7

    Lay and level

    gel: 2 h · 20 min

    Pour the mix onto the reinforced floor, spread it and level it with a flat trowel at 3 mm. Work carefully into edges, corners, doorways and transitions, keep an even depth and a wet edge, and plan your route so you don’t trap yourself.

    TipDon’t overwork it once the finish is there: late trowelling can spoil it. Slow Set gels in 2 hours; Fast Set in 20 minutes at 15 °C.

    • Flat steel trowel
    • Straight edge
  8. 8

    Finish it

    Leave the screed as it is, roll on a clear R.S Urethane Topcoat in gloss, satin or matt, or go on to a compatible decorative system: Spray Granite, Spray Stone or an R.S.P decorative pour.

    TipOverlaying another system? Check it’s compatible with P.HB first, or ask your Infinity rep. If you miss the recoat window, abrade mechanically, vacuum and re-establish the bonding profile.

    • Roller
  9. 9

    Protect it while it cures

    48 h · 6–8 h

    Keep foot and wheeled traffic, equipment, water, dust and other trades off it until it has cured: 48 hours before use for Slow Set, traffic after 6–8 hours for Fast Set (recommended). Check it’s firm, even and undamaged before opening it up.

    TipDon’t judge readiness by touch alone.

Mesh laid over a tiled floor before screeding, by H53 Coatings
H53 Coatings · Mesh over tiles · September 2025See the job →
Screed being laid with a trowel, the kit weighed out on scales, by H53 Coatings
H53 Coatings · Laying the screed · September 2025See the job →
Timings

Gel, dry, use: the clock that runs the job.

Drag the slider from the moment the screed is mixed.

  1. 2 hoursGel time: stop working the screed
  2. 24 hoursFull dry
  3. 48 hoursReady for use (recommended)

Warmer conditions shorten the working time and speed up the cure; cooler conditions lengthen both. Retarders are allowed only if we’ve approved them, and extra working time also extends the cure.

Kit estimate

How much you’ll need.

A quick estimate from our coverage figures. Build Your P.HB Screed System works out the primer and mesh for your floor, with prices.

Use the builder for your exact kit list. Build your P.HB Screed system

Real jobs

P.HB floors on real jobs.

Over tiles and concrete, laid by our fitters.

FAQ

Questions we get asked

Can P.HB Screed go over tiles?

Yes, over existing, sound, firmly bonded tiles. Take up any loose, broken or cracked ones and fill the gaps first. AdhesiMesh Lite is required over tiles, to bridge the joints.

How thick is it?

It’s laid at 3 mm. One 15 kg kit covers about 3 m².

Do I need the mesh on concrete?

It’s recommended on concrete, to reinforce the screed and reduce the risk of cracking, and required over tiles.

How much primer does my floor need?

About 7.5 m² per kg on dense concrete. Medium porosity takes 1.5×, high porosity 2×, and tiles 1.5×. Do the water-drop test to check.

Slow Set or Fast Set?

Same price. Slow Set gels in 2 hours and is ready for use after 48 hours. Fast Set gels in 20 minutes at 15 °C and takes traffic after 6–8 hours, so it suits small, quick-return jobs.

Can I put Spray Granite on top?

Yes. P.HB is the base for Spray Granite, Spray Stone and R.S.P decorative pours. Check compatibility with your rep before you order another system.

Downloads & tools
Having it done?Find an Infinity-trained installer near youFind an installerInstalling it yourself?Learn the system at an Infinity Effects certified schoolSee the training

Keep reading

All news & guides

Leave a Comment

Your email address will not be published. Required fields are marked *

Shopping Basket