How to install P.HB Screed over concrete or tiles
P.HB Poly Screed goes straight over prepared concrete or sound tiles at 3 mm. Here’s each build-up, every step from prep to cure, the timings and how much you’ll need.
Over concrete or tiles, one flexible screed.
P.HB Poly Screed is a fast-curing, high-impact polyaspartic hybrid screed that flexes with movement in the floor. Laid at 3 mm over R.S.P Primer and AdhesiMesh Lite, it’s a finished floor on its own, or the base for Spray Granite, Spray Stone or a decorative pour.
- 3 mmlaid thickness
- ≈ 3 m²per 15 kg kit
- 2 h · 20 mingel time, Slow Set · Fast Set
- 48 h · 6–8 hback in use, Slow Set · Fast Set

Three build-ups, four layers each.
Concrete, straight over tiles, or as the base for a decorative finish. Tap a layer for the product, coverage and timings.
Spread with a squeegee or rubber grout trowel for continuous, even coverage: no dry patches, pooling, missed edges or excess build-up.
- Coverage
- About 7.5 m² per kg on dense concrete
- Porous
- Medium porosity takes 1.5×, high porosity 2×
Pre-cut to suit the area, laid into the wet primer and pressed flat, with no wrinkles, folds or raised sections. Recommended on concrete to reinforce the screed.
- Rolls
- 1 m × 50 m and 1 m × 100 m
- Overlaps
- Allow about 10%
A UV-stable aliphatic polyaspartic hybrid screed, mixed 4:1:1 (screed mix : Part A : Part B), poured onto the reinforced floor and levelled with a flat trowel at 3 mm. It flexes with movement in the floor and reduces the risk of cracking.
- Coverage
- About 3 m² per 15 kg kit at 3 mm
- Gel time
- Slow Set 2 hours · Fast Set 20 minutes
- Colours
- White, POLY colours or any RAL match
A clear water-based sheen coat over the screed, rolled on evenly.
- Coverage
- About 15 m² per kg
Spread with a squeegee or rubber grout trowel for continuous, even coverage: no dry patches, pooling, missed edges or excess build-up.
- Coverage
- Tiles take 1.5× the base rate of about 7.5 m² per kg
Pre-cut to suit the area, laid into the wet primer and pressed flat, with no wrinkles, folds or raised sections. Required over tiles to bridge the joints.
- Rolls
- 1 m × 50 m and 1 m × 100 m
- Overlaps
- Allow about 10%
A UV-stable aliphatic polyaspartic hybrid screed, mixed 4:1:1 (screed mix : Part A : Part B), poured onto the reinforced floor and levelled with a flat trowel at 3 mm. It flexes with movement in the floor and reduces the risk of cracking.
- Coverage
- About 3 m² per 15 kg kit at 3 mm
- Gel time
- Slow Set 2 hours · Fast Set 20 minutes
- Colours
- White, POLY colours or any RAL match
A clear water-based sheen coat over the screed, rolled on evenly.
- Coverage
- About 15 m² per kg
Spread with a squeegee or rubber grout trowel for continuous, even coverage: no dry patches, pooling, missed edges or excess build-up.
- Coverage
- Depends on the floor and its porosity
Pre-cut to suit the area, laid into the wet primer and pressed flat, with no wrinkles, folds or raised sections. Over concrete or tiles.
- Rolls
- 1 m × 50 m and 1 m × 100 m
- Overlaps
- Allow about 10%
A UV-stable aliphatic polyaspartic hybrid screed, mixed 4:1:1 (screed mix : Part A : Part B), poured onto the reinforced floor and levelled with a flat trowel at 3 mm. It flexes with movement in the floor and reduces the risk of cracking.
- Coverage
- About 3 m² per 15 kg kit at 3 mm
- Gel time
- Slow Set 2 hours · Fast Set 20 minutes
- Colours
- White, POLY colours or any RAL match
P.HB as the base, with Spray Granite, Spray Stone or an R.S.P decorative pour on top. Each follows its own system guide.
- Check first
- Confirm the system on top is compatible with P.HB, or ask your Infinity rep
The install, one step at a time.
These steps follow our P.HB Poly Screed application guide. Set everything up before you mix: with Fast Set, the clock starts fast.
- 1
Check the floor
It must be sound, dry, stable, clean and free of contamination. Look for laitance, old coatings, oil, grease, adhesive residue, loose concrete, cracks, holes and unsound repairs.
TipDon’t use the screed to make up for an unstable, contaminated or poorly prepared floor, and never lay it over standing water, condensation or wet cleaning residue.
- 2
Prepare concrete or tiles
Concrete: grind to CSP 2–3 where practicable, taking extra care at edges, corners, doorways, drains and perimeters, and repair cracks, voids, holes and damaged edges. Tiles: take up loose, broken or cracked tiles, fill the gaps, deep grout joints and holes, degrease and remove all cleaner residue, then sand to take off the gloss and give a key.
TipOur prep guide has the detail for each floor, including the porosity test.
- Floor grinder, diamond tooling
- Edge grinder
- PolyFuse MAX filler
- 3
Vacuum
Industrially vacuum the whole area, leaving no loose dust anywhere.
- Industrial vacuum
- 4
Prime
Mix R.S.P Primer and spread it with a squeegee or rubber grout trowel for continuous, even coverage, with no dry patches, pooling, missed edges or excess build-up. Porous concrete takes more primer: 1.5× for medium porosity and 2× for high; tiles take 1.5×.
- Squeegee
- Rubber grout trowel
- 5
Lay the mesh
Pre-cut AdhesiMesh Lite to suit the area, avoiding small offcuts. Lay it into the wet primer and press it firmly so it lies flat, with no wrinkles, folds or raised sections. Keep it continuous through doorways, repairs, tile joints, transitions and perimeters, with no loose mesh sticking up.
TipMesh is required over tiles to bridge the joints, and recommended on concrete.
- Knife or scissors
- Measuring tape
- 6
Mix the screed
Use complete, matched kits and never estimate ratios. Combine Part A and Part B and mix for at least 30 seconds, then add the screed mix gradually while mixing. Keep going for 2–3 minutes until it’s uniform and fully wetted, with no lumps or dry pockets, scraping the sides and base.
TipDon’t add water, solvent or additives unless we’ve authorised them, and don’t leave mixed material sitting in the bucket.
- Mixing drill
- Heavy-duty paddle
- Clean containers
- 7
Lay and level
gel: 2 h · 20 minPour the mix onto the reinforced floor, spread it and level it with a flat trowel at 3 mm. Work carefully into edges, corners, doorways and transitions, keep an even depth and a wet edge, and plan your route so you don’t trap yourself.
TipDon’t overwork it once the finish is there: late trowelling can spoil it. Slow Set gels in 2 hours; Fast Set in 20 minutes at 15 °C.
- Flat steel trowel
- Straight edge
- 8
Finish it
Leave the screed as it is, roll on a clear R.S Urethane Topcoat in gloss, satin or matt, or go on to a compatible decorative system: Spray Granite, Spray Stone or an R.S.P decorative pour.
TipOverlaying another system? Check it’s compatible with P.HB first, or ask your Infinity rep. If you miss the recoat window, abrade mechanically, vacuum and re-establish the bonding profile.
- Roller
- 9
Protect it while it cures
48 h · 6–8 hKeep foot and wheeled traffic, equipment, water, dust and other trades off it until it has cured: 48 hours before use for Slow Set, traffic after 6–8 hours for Fast Set (recommended). Check it’s firm, even and undamaged before opening it up.
TipDon’t judge readiness by touch alone.


Gel, dry, use: the clock that runs the job.
Drag the slider from the moment the screed is mixed.
- 2 hoursGel time: stop working the screed
- 24 hoursFull dry
- 48 hoursReady for use (recommended)
- 20 minGel time at 15 °C
- 2 hoursDry
- 6–8 hoursReady for traffic (recommended)
Warmer conditions shorten the working time and speed up the cure; cooler conditions lengthen both. Retarders are allowed only if we’ve approved them, and extra working time also extends the cure.
How much you’ll need.
A quick estimate from our coverage figures. Build Your P.HB Screed System works out the primer and mesh for your floor, with prices.
Use the builder for your exact kit list. Build your P.HB Screed system
P.HB floors on real jobs.
Over tiles and concrete, laid by our fitters.
More in the P.HB Screed guide series
Questions we get asked
Can P.HB Screed go over tiles?
Yes, over existing, sound, firmly bonded tiles. Take up any loose, broken or cracked ones and fill the gaps first. AdhesiMesh Lite is required over tiles, to bridge the joints.
How thick is it?
It’s laid at 3 mm. One 15 kg kit covers about 3 m².
Do I need the mesh on concrete?
It’s recommended on concrete, to reinforce the screed and reduce the risk of cracking, and required over tiles.
How much primer does my floor need?
About 7.5 m² per kg on dense concrete. Medium porosity takes 1.5×, high porosity 2×, and tiles 1.5×. Do the water-drop test to check.
Slow Set or Fast Set?
Same price. Slow Set gels in 2 hours and is ready for use after 48 hours. Fast Set gels in 20 minutes at 15 °C and takes traffic after 6–8 hours, so it suits small, quick-return jobs.
Can I put Spray Granite on top?
Yes. P.HB is the base for Spray Granite, Spray Stone and R.S.P decorative pours. Check compatibility with your rep before you order another system.
Keep reading
All news & guides
One factory, every surface: which Infinity system?Which Infinity system for your project? Pick the surface, from worktops and kitchen doors to floors, walls, driveways, uPVC and furniture, and see the system.26 Nov 2026 · 4 min readRead the guide
Start a coatings business with InfinityHow to start a coatings business with Infinity Effects: pick your services, train and certify, open a trade account, get found and grow.26 Nov 2026 · 3 min readRead the guide
How to order from Infinity EffectsHow to order from Infinity Effects: set up your account, build your kit list, check out and choose delivery, with dispatch times and where we ship.26 Nov 2026 · 3 min readRead the guide